August 24, 2021
Ops Notice 2021-035

TMX Group

TMX Operational Notice

TMX Disaster Recovery Network Connectivity Test

In addition to the Disaster Recovery Dates for 2021 announced February 18th - Operational Notice 2021-008, TMX will be facilitating a pre-connectivity test to be held on Saturday, September 11th 2021 in relation to the TMX, IIROC and FIA External Disaster Recovery Test that is scheduled for October 23rd 2021.

The purpose of the pre-connectivity test is to provide clients the opportunity to establish and confirm network connectivity to the Toronto Computing Facility (TCF) DR data centre.

TMX will simulate a "disaster" at the primary data centre and failover TMX's primary trading and market data feed delivery systems to backup systems at the TCF DR site.

This activity is intended for clients to confirm DR site network connectivity. Clients are advised to verify using telnet to Unicast destinations (OE sessions; Feed Recovery Sessions). TMX does not support PING and therefore cannot be used for verification.

Participants can test Pre-Connectivity with the following services:

SAIL FIX ATR
Drop Copy TMS Clearing API
MX FTP/SFTP Server
(EOD and PAR Reports)
LOPR HSVF (unicast & multicast)
OBF (Order Book Feed) TSX, TSX Venture, TSX Alpha - Production (Telnet to Unicast destinations, OE sessions; Feed Recovery Sessions) OBF (Order Book Feed) TSX, TSX Venture, TSX Alpha - Production - Multicas

Pre-Connectivity Test - September 11th, 2021
Participants Start Time 10 h
Participants End Time 13 h

As long as testing is conducted between 10:00 am to 1:00 pm ET, no testing appointments are required.

TMX Market Operations will be available for support during the test. Participants are asked to advise the Technical Support Desk by phone or email once they have successfully completed connectivity testing.

** Please provide your email to TMX Market Operations if you are participating in the DR testing **

**A future notice will be sent providing details and timelines for the FIA / IIROC Disaster Recovery Test to be held on October 23, 2021**